Task

Bolting the stabilizer to the rear axle carrier. The system must be designed as a semi-automatic system. Delivery in the Z-axis is pneumatic. The adaptation must be pinned on the rear axle carrier. Bolting is carried out with two spindles per side with pneumatic feed. After bolting, the system moves back to the park position in the Z-axis.

Special feature: Semi-automatic

Torque: 4x 48Nm

Payload: 60 kg

 

handy-lift

Equipment
Equipment
1
crane rail
2
Energy supply
3
carne bridge
4
handy-lift 500
5
Weight compensation
6
Fall protection
7
Pneumatic feed
8
handy-lift adaptation system

Adaptation system

Equipment
Equipment
1
Rotary unit
2
Swivel joint
3
Operating handle
4
Pneumatic feed
5
Pinning
6
Spindle